The latest update on the Edinburgh Tram Project is set to go before Councillors next week.
The report, to be presented to the Full Council meeting of the City of Edinburgh Council on Thursday 24 June, will set out the current position on construction progress, the contractual dispute, tie’s strategy for resolving the dispute along with options for moving the project forward.
Whilst progress is behind schedule, the report details that works on the off-street section of the route, including the tram depot at Gogar, the bridges at Edinburgh Park and Carrick Knowe, the guided busway and the viaduct at Haymarket are now advancing. Construction and testing of the fleet of 27 tram vehicles is well underway with the first tram now on Princes Street as a popular public exhibit.
The massive job to divert utility pipes and cables increased by some 85% above the amount originally programmed, this work is now substantially complete and is a considerable betterment of the city’s underground infrastructure.
Since early 2009, much of the public focus of the project has centred around the contractual dispute with the Consortium of Bilfinger Berger, Siemens and CAF (BSC).
The report notes that relationships with two of the contractors, Siemens and CAF, remain largely positive. The dispute is largely related to the infrastructure installation works and there are three areas which make up the current impasse:
* The apparent adoption by BSC of an approach of not progressing works where there is a change, or alleged change, to the contracted scope of works until the financial entitlements from the change are definitively resolved. This appears inconsistent with the terms of the Agreement which states that works be undertaken while a resolution is found.
* Design-related matters. While the agreement reached by all parties was for a fixed-price lump sum contract, tie has accepted that certain elements are legitimate additions to the price. For example; extra demolition works and soft-ground treatment. The issue at dispute is whether individual matters constitute changes to the original scope of works and whether a change to the design justifies additional payment. A formal contractual process, known as Dispute Resolution Process (DRP) has been employed to find solutions for these individual issues.
* Delays to programme caused by further time required to complete additional utility diversion work. tie has already offered what they determine as a reasonable amount of time to add onto the works programme, however agreement has yet to be reached.
Cllr Gordon Mackenzie, Transport Convener at the City of Edinburgh Council, said: “This report brings much greater clarity to the people of Edinburgh regarding all aspects of the tram project. It also dispels some of the myths that others have used politically regarding potential levels of overspend.
“As a public body, the Council must prudently manage any risk and the Directors’ suggestion of adding a 10 per cent contingency figure is reasonable to work with as we look at our various options.
“Of course if we were not in dispute with the contractor there would be no need to do this. While signs of progress at the west of the city, tram vehicle production and the finalisation of utility works are welcome, we are by no means in the position we would like to be. I am fully-supportive of the lengths tie’s management have gone to in trying to resolve the contractual dispute against a background of continual frustration and public scrutiny."
(GK)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...