The Scottish Government has today laid before Parliament two Orders to extend the time limits for the City of Edinburgh Council (CEC) to compulsorily acquire the land needed to complete its trams project.
CEC requested the extension of these powers under provisions in the Edinburgh Tram Acts authorising construction. The extensions are needed to enable the project to move forward after resolution of the current contractual dispute.
The contractual dispute between CEC/tie and its contractors has significantly delayed the project beyond its original completion date of Summer 2011 and this has directly led to CEC’s application for additional time to complete the land acquisition.
Keith Brown, Transport Minister, said: “The Scottish Government's position on Edinburgh trams is clear. We opposed the project, but in June 2007 the Scottish Parliament voted that we provide funding to a maximum of £500m. The project is and always has been the responsibility of City of Edinburgh Council.
“We want to ensure that nothing stands in the way of delivering trams for the benefit of the people of Edinburgh. Given the delays caused by the current contractual dispute not extending these powers of land acquisition would seriously compromise the Council’s ability to complete the project.
“The Scottish Government is simply not prepared to place the people of Edinburgh and the public purse in such a position.”
Mr Brown also reiterated the Scottish Government’s commitment to assist the Council in resolving the project’s current difficulties.
“With mediation due to start next month (March) it is not the right time to be discussing substantial changes to the governance of the project. However, we want to ensure that every opportunity is taken to resolve this long running dispute so that a tram service can be delivered in Edinburgh, and have agreed that Transport Scotland will take part in the mediation process.”
The two Acts (the Edinburgh Tram (Line One) Act 2006 and the Edinburgh Tram (Line Two) Act 2006) provide for CEC to construct and operate the tram line between Edinburgh Airport and Leith. The powers of compulsory acquisition were granted for an initial period of five years and are due to expire in April and May 2011 for Line Two and Line One respectively. The powers can be extended for a further period by Order of the Scottish Ministers following an application from CEC. The extensions provided by the Orders are for five (Line 1) and ten years (Line 2).
As a result of the delay arising from the current contractual dispute, it would otherwise not be possible within the time remaining to complete the acquisition of all the land required - a small amount of land between the airport and St Andrew Square and some larger parcels of land, most of which are in the north-east part of the City.
The Orders come into force on 1 April 2011.
(GK)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...