The way forward for the tram project is clearer today with one of the proposals agreed through the mediation process being made public.
Following the mutually agreed appointment of an independent mediator, Michael Shane, intensive meetings took place from 8 - 12 March with all relevant parties represented. In the two months since, positive dialogue has been maintained.
A key outcome of the process has been that the parties have set aside their differences in respect of Princes Street and the infrastructure contractor, Bilfinger Berger and Siemens (BBS) has agreed that it will carry out a programme of remedial works to fully repair the road surface. The works will be carried out in two stages: from 3 July - 26 November and then from January - May next year. No new public funds will be required for these works.
Other works on Princes Street will also be undertaken including erecting street lighting and remaining overhead line equipment poles and work around the tram stop.
Over the coming period, prior to the diversions being implemented, the Council and the infrastructure contractor will carry out a detailed consultation with the city centre business community, and other key stakeholders, to plan the necessary arrangements for traffic diversions, bus services, pedestrian routes, waste collection, deliveries and signage.
Traffic diversion arrangements will be broadly similar to those in place during previous works, with buses, taxis and cycles diverted to George Street and general traffic diverted onto Queen Street as a principal route.
Leader of the City of Edinburgh Council, Cllr Jenny Dawe, said: "Last November I instructed the Chief Executive to pursue the option of mediation with tie and the infrastructure contractor and I am pleased that we are now seeing the benefits of this process.
"Without question there is a difficult period ahead, however I am still of the belief that a tram network which expands over time will be of enormous benefit to people living and working in this city for generations to come.
"The programme of priority works along with rectifying the road surface and other works on Princes Street is a sign that we are moving forward. We had hoped to avoid the scenario of a further traffic diversion from Princes Street but having listened to the advice from council officers and the infrastructure contractor I understand why this is necessary. We will work closely with the city's business community to ensure any impact is managed effectively before the diversion is put in place and during the period of works."
Vic Emery, Chair of tie, added: "It was vital that the momentum of the project was restored. All parties involved are in agreement that, through the mediation process, good progress has been made in identifying the key issues that lay at the heart of the dispute, and a measure of goodwill has been re-established.
"The next step is to finalise the revised plans for the delivery of phase 1a, including projected costs and programme, and this will be shared with all relevant parties including Transport Scotland and the Scottish Government before being made public in due course."
Martin Foerder, Project Director for Bilfinger Berger Civil UK Ltd commented: "There are a number of outstanding elements still to be undertaken on Princes Street and by doing these now we are also able to repair the road surface.
"Bilfinger Berger, Siemens and CAF are committed to working with partners in Edinburgh to deliver a tram system for the city and have already completed a number of significant structures as well as the building of the tram vehicles.
"I look forward to being able to announce shortly the plans for the remaining works still to be undertaken which will see trams running from the airport to the city centre."
A full programme of consultation with city stakeholders affected by the Princes Street programme will be undertaken, including an analysis of any opportunities which may arise to use the increased availability of pedestrian space.
(GK)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...