Repair work being undertaken on the Burntisland clock tower in Fife has uncovered the cause of the structural damage.
The problems initially occurred following the discovery of damage to the tower. Work was then carried out to remove the affected stone.
But this week the further removal of two of the tower’s bells by stonemasons uncovered the core of the problems; a rusted iron hoop in the middle of the stonework at the level of the cracked arches.
Alan Paul, Senior Manager explained: "A wrought iron hoop had been built into the middle of the wall, just behind the apex of the lancet arches. This was probably used to reinforce the tower, in order to prevent the walls spreading due to the weight of the spire.
"It is very badly corroded and when iron and steel corrode they expand. This expansion results in significant force on the stone, pushing it out, causing it to crack and also forcing the joints open.
"The hoop is located immediately behind the worst areas of damage to the stone and has expanded significantly, so we are certain that this is the cause. The rest of the affected sections of stone will now be removed.
"The remaining two bells will also be taken out using a block and tackle so there should be no further need to use the crane and traffic control, unless we come across some particularly large blocks of stone."
When the dismantling work has been carried out, a temporary roof will be put in place to weatherproof the tower.
The tower will then be put back together using as much of the original stone as possible.
In addition, the clock mechanism has been removed to keep it safe during the works.
(IT/GK)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
29/11/2024
Construction has begun on the initial phase of Spaceport 1, a sub-orbital launch site in the Outer Hebrides. Local contractor, Macaulay Askernish Ltd, has been awarded a contract by Comhairle nan Eilean Siar to undertake enabling works at Scolpaig Farm in North Uist. The project, funded by a £947k ...
29/11/2024
David Smith Contractors Ltd, a local firm based in Fraserburgh, has been awarded a multi-million-pound contract to contribute to the construction of the Eastern Green Link 2 (EGL2) project. The company will undertake civil engineering works at the converter station site near Boddam, Peterhead. ...
29/11/2024
Scotland has unveiled a new plan to become a leading exporter of renewable hydrogen by 2030. The plan, titled 'A Trading Nation: Realising Scotland's Hydrogen Potential – A Plan for Exports', outlines specific actions needed to achieve this goal. The Scottish Government aims to capitalize on the ...
29/11/2024
First Minister John Swinney has welcomed the progress being made in the construction of the new Perth High School during a recent site visit. The new three-storey building, being delivered by Robertson Construction Tayside on behalf of hub East Central Scotland, will accommodate up to 1,600 pupils ...
29/11/2024
Glasgow City Council has given the green light to the sale of four land plots in the city to facilitate various development projects. The sites in question are located in Carmyle, Deaconsbank, Maryhill, and Port Dundas. The disposals are expected to generate significant capital receipts for the ...
29/11/2024
Scottish Water is set to achieve a significant milestone in its woodland creation programme, planting over 500,000 trees by the end of the current planting season in March 2025. This year, the company will plant more than 245 hectares of native woodland across various sites, including Loch ...
28/11/2024
Construction has begun on a new £33 million student accommodation development in Glasgow city centre. The project, a partnership between Artisan Real Estate and Homes for Students, will provide 321 self-contained studio apartments at 292-298 St Vincent Street. The existing office building on the ...
28/11/2024
Springfield Properties has submitted detailed plans to Midlothian Council for the first phase of its new Lingerwood development. The proposed development, located off Stobhill Road near Newtongrange, will eventually include around 1,000 homes. The first phase will comprise 63 homes, ranging from ...
28/11/2024
Scottish Land & Estates (SLE) has called on the Scottish Government to prioritise the needs of rural communities in the upcoming Scottish Budget. Dee Ward, Chair of SLE, has urged the Finance Secretary, Shona Robison, to conduct a robust rural impact assessment for all spending and taxation ...
28/11/2024
Four Scottish electrical apprentices have been praised for their performance in the prestigious SkillELECTRIC competition. John-Ross Campbell, Kalum Low, Milly Smith, and Ewan Thomas, all SETCTT apprentices, represented Scotland in the UK-wide competition, which was held at Oldham College. Milly ...