The new £1.35 billion Queensferry Crossing will not open until between mid-July and the end of August, it has been announced.
Speaking to the Parliament's REC Committee today, 29 March, Economy Secretary Keith Brown confirmed the structure will open around four to 10 weeks later than expected.
The blame has been put down to there being fewer clear weather windows than expected, particularly in relation to wind. This has delayed weather dependant activities, causing them to clog together at the end of the construction programme to a much greater degree than was anticipated in May last year.
Weather dependent works include moving the tower cranes, which can only be removed in wind speeds of below 25mph. Even when this is happening, it is not possible to carry out safety work in a 50 metre radius of the machine itself.
Other weather affected phases include work on cable stays, waterproofing the bridge deck and road surfacing.
With lots of construction activity underway at the same time, Mr Brown emphasised it is important to "take the time to make sure the bridge is built in the safest possible circumstances to the highest possible standards".
"Today there are only nine weeks remaining to the end of May and the review has concluded that even with the best weather this date is not now safely achievable," he said.
"I fully recognise the effort of the workforce in building this amazing new bridge. Over 13 million hours have gone into building the Queensferry Crossing over the past six years.
"There is no additional cost to the public purse and the Forth Road Bridge continues to carry traffic over the Forth during these final weeks of construction. While its clearly very disappointing the new bridge won't be ready ahead of the contractual completion date, I believe it is important to take the time to make sure the bridge is built in the safest possible circumstances to the highest possible standards."
Sally Cox, chair of the Board for the Forth Road Crossing Bridge Constructors (FCBC), the consortium behind the project, said: "FCBC acknowledge that the uniqueness of this project and the onerous weather conditions it has experienced, particularly working at height crossing the Forth have created more challenges than we anticipated.
"FCBC have always been and remain ambitious about completing this challenging project at the earliest possible date and share Transport Scotland and the public's frustration over this delay. We have assured Transport Scotland that every endeavour is and will continue to be made, to safely complete the project at the earliest opportunity."
(LM/MH)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
29/11/2024
Construction has begun on the initial phase of Spaceport 1, a sub-orbital launch site in the Outer Hebrides. Local contractor, Macaulay Askernish Ltd, has been awarded a contract by Comhairle nan Eilean Siar to undertake enabling works at Scolpaig Farm in North Uist. The project, funded by a £947k ...
29/11/2024
David Smith Contractors Ltd, a local firm based in Fraserburgh, has been awarded a multi-million-pound contract to contribute to the construction of the Eastern Green Link 2 (EGL2) project. The company will undertake civil engineering works at the converter station site near Boddam, Peterhead. ...
29/11/2024
Scotland has unveiled a new plan to become a leading exporter of renewable hydrogen by 2030. The plan, titled 'A Trading Nation: Realising Scotland's Hydrogen Potential – A Plan for Exports', outlines specific actions needed to achieve this goal. The Scottish Government aims to capitalize on the ...
29/11/2024
First Minister John Swinney has welcomed the progress being made in the construction of the new Perth High School during a recent site visit. The new three-storey building, being delivered by Robertson Construction Tayside on behalf of hub East Central Scotland, will accommodate up to 1,600 pupils ...
29/11/2024
Glasgow City Council has given the green light to the sale of four land plots in the city to facilitate various development projects. The sites in question are located in Carmyle, Deaconsbank, Maryhill, and Port Dundas. The disposals are expected to generate significant capital receipts for the ...
29/11/2024
Scottish Water is set to achieve a significant milestone in its woodland creation programme, planting over 500,000 trees by the end of the current planting season in March 2025. This year, the company will plant more than 245 hectares of native woodland across various sites, including Loch ...
28/11/2024
Construction has begun on a new £33 million student accommodation development in Glasgow city centre. The project, a partnership between Artisan Real Estate and Homes for Students, will provide 321 self-contained studio apartments at 292-298 St Vincent Street. The existing office building on the ...
28/11/2024
Springfield Properties has submitted detailed plans to Midlothian Council for the first phase of its new Lingerwood development. The proposed development, located off Stobhill Road near Newtongrange, will eventually include around 1,000 homes. The first phase will comprise 63 homes, ranging from ...
28/11/2024
Scottish Land & Estates (SLE) has called on the Scottish Government to prioritise the needs of rural communities in the upcoming Scottish Budget. Dee Ward, Chair of SLE, has urged the Finance Secretary, Shona Robison, to conduct a robust rural impact assessment for all spending and taxation ...
28/11/2024
Four Scottish electrical apprentices have been praised for their performance in the prestigious SkillELECTRIC competition. John-Ross Campbell, Kalum Low, Milly Smith, and Ewan Thomas, all SETCTT apprentices, represented Scotland in the UK-wide competition, which was held at Oldham College. Milly ...