A83 Improvements At Strone Point To Start In December

Construction News Image
Road improvement works are set to begin on the A83 at Strone Point outside Inveraray next month.

The 28-week project aims to improve the radius of the tight corner at Strone Point and will get underway on 04 December.

Features include;

• realigning the carriageway and cutting back the rock slope to improve visibility for drivers

• improving the road width

• upgrading the drainage systems to improve road safety in wet conditions

• erecting a new road safety barrier and bike guard

-- Advertisement --
NorthernAsbestosServicesLtd

• new road markings

• improved signing

Transport Minister, Humza Yousaf said: "We know that the local community has been waiting for this work to get underway for some time and we are pleased to have agreed a programme with the contractor that will keep the A83 open for the majority of the project.

"Everything possible will be done to minimise disruption, especially during the festive period when traffic management will be removed between 22nd December 2017 and 3rd January 2018.

"The patience that people have shown so far is very much appreciated and we are expecting to see progress now that the works schedule has been agreed."

Transport Scotland said during the vast majority of the programme, the road will be reduced to one lane and controlled by temporary traffic signals. In addition, up to 13 night time road closures will be required and road users will be notified in advance.

(LM/MH)

Latest Construction News

15/11/2024

A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024

Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024

The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024

Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024

Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit.  The ambitious project will involve a range of ...
15/11/2024

The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024

Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024

Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024

The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024

BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...
RBT Underfloor LimitedMorris & Spottiswood LtdToner Damp Proofing SuppliesNo HydroSEEIT3DCF Concrete PumpingMaccaferri LtdSMS Alba LimitedDiscount Kitchens and Bathrooms LtdShopfronts Scotland
Terms and Conditions
2024/11/16 06:23:40