An Initial Needs Case (INC) has been submitted on a proposal to replace the existing Fort Augustus to Skye electricity transmission line by SSEN Transmission to Ofgem.
The INC, which is part of Ofgem's new Large Onshore Transmission Investment (LOTI) Uncertainty Mechanism for the RIIO-T2 price control period, is the first stage of the regulatory funding approvals process.
At an estimated cost of around £400m, the Skye reinforcement project would be one of the most significant energy investments in the West Highlands since power was first brought to the area in the 1950's.
The existing Fort-Augustus to Skye line, which was constructed in three distinct sections between 1956 and 1989, consists of a combination of steel lattice towers from Fort Augustus to Broadford, then overhead wooden poles from Broadford to Edinbane. The line is fast reaching the end of its operational life and is in urgent need of intervention. Its planned replacement is therefore essential to maintain network reliability and security of supply to homes and businesses along its route, as well as to the Western Isles which is primarily supplied by two electricity distribution subsea cables from Ardmore point.
To enable the connection of new renewable electricity looking to connect to the transmission network along its route, SSEN Transmission is also proposing to increase the capacity of the replacement line, supporting the UK and Scottish Governments transition to net zero emissions. The existing line has already exceeded its capacity limit, preventing the connection of new renewable electricity in the area.
Rob McDonald, Managing Director of SSEN Transmission, said: "Submission of our Initial Needs Case marks a major milestone in unlocking the significant investment required for the Skye reinforcement project. The project is essential to maintain and improve network reliability and security of supply, whilst also supporting local and national efforts to tackle the climate emergency and deliver a pathway to net zero emissions.
"We now look forward to working constructively with Ofgem and our stakeholders to make the investment required in a timely manner, delivering on Ofgem's commitment to an agile and flexible regulatory framework and in doing so, create hundreds of skilled jobs throughout the supply chain to support a green recovery from the coronavirus pandemic."
Given the scale of the project, stakeholders have made it clear the replacement line should anticipate future electricity generation looking to connect in the years ahead, avoiding an iterative approach to network development and associated local impacts and disruption this would cause. This 'do it once do it right' approach, which the Electricity System Operator's own independent Cost Benefit Analysis (CBA) supports, will greatly reduce the need for additional major works in the future, responding positively to stakeholders asks.
To meet the required increased capacity of the replacement line, steel structures will be required from Fort Augustus to Edinbane; with wooden pole remaining from Edinbane to Ardmore. Upgrades to the existing substations at Broadford and Edinbane will also be required as part of the Skye reinforcement.
SSEN Transmission continues to progress the detailed design for the replacement line and expects to consult on its preferred route and technology later in the autumn. As part of this and in response to stakeholder feedback, SSEN Transmission is actively exploring potential mitigations. This includes assessing the potential for undergrounding as the line passes the Cuillin Hills and where it connects to Fort Augustus substation; and alternative routes as it passes Kylerhea.
Separately, work to progress a 600MW HVDC connection to the Western Isles continues with SSEN Transmission committed to continuing to work constructively with Ofgem, Government, Western Isles generators and wider stakeholders to overcome barriers to unlock the islands vast renewables potential.
Time and date
CONSTRUCTION DIRECTORY
Construction News
03/08/2021
SSEN Propose Skye Electricity Transmission Line Replacement
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...