20/08/2021

Construction Progressing On New East Dunbartonshire Development

Construction News Image
East Dunbartonshire Council has welcomed the progress being made in the construction on the multi-million pound Allander Leisure and Day Care Centre.

The Council is redeveloping the current Bearsden site as part of a £42.5 million investment - including a new, state-of-the-art sports and leisure complex, as well as a support centre for adults with learning disabilities.

Work is being carried out in phases, with the first - construction of the new Allander Leisure and Day Care Centre - beginning in January this year.

The foundations have been successfully laid and construction of the steel frame is almost complete - with the final bolts being put in. Main contractor McLaughlin & Harvey plans to commence 'envelope works' in the coming weeks, which will include roofing, walls, windows, doors, floors and more.

The centre is due to open in autumn 2022, with the final project forecast to be completed by summer 2023. Phase two involves the decommission and demolition of the existing leisure centre, with phase three being the construction of a new 'Sportsdrome' and final car park works.

Councillor Vaughan Moody, Joint Leader of the Council, said: "I am delighted to see a new era taking shape for the Allander, with work progressing well on this state-of-the-art project. It's an exciting time for everyone involved as we look forward to welcoming this multi-million pound complex - including support facilities for adults with learning disabilities.

-- Advertisement --
NorthernAsbestosServicesLtd

"We have worked with our partners to ensure the existing Allander Leisure Centre is able to continue to operate, where possible, while work is carried out."

Councillor Andrew Polson, Joint Leader of the Council, added: "It has been a long road to reach this milestone stage and I want to thank everyone who has taken part in the journey - including local residents, organisations and partners.

"Allander Leisure and Day Care Centre represents a major capital investment by the Council and will help to change local lives for the better. I can't wait to welcome the completed project, which will offer a range of facilities to help inspire and support people of all ages."

The new Allander Leisure and Day Care Centre will include:

• An eight-lane swimming pool and a 20m training pool with movable floor

• Sauna and steam vitality room

• Hydrotherapy pool

• Gym and high & low intensity studios

• State-of-the-art spin room

• Eight-court games hall

• Two squash courts

• Wet and dry changing facilities

• Café

• 'Sportsdrome' - including two football pitches and a tennis court.

There will also be a new support facility created for adults with learning disabilities - replacing Kelvinbank Resource Centre in Kirkintilloch - which will include:

• Flexible meeting rooms, quiet spaces and office

• Dementia, rebound, sensory and physiotherapy treatment rooms

• Arts & crafts, dance and music rooms

• State-of-the-art changing rooms

• Training kitchen for learning.

McLaughlin & Harvey is the main contractor and architectural design is by Holmes Miller, with support from Doig+Smith, Brown + Wallace and planning consultancy Barton Willmore.

Work has been carried out with partners including East Dunbartonshire Leisure and Culture Trust, and East Dunbartonshire Health and Social Care Partnership.

As part of the agreement with McLaughlin & Harvey, the contractor has engaged with the community throughout the project.

Managing Director Paul Griffen said: "McLaughlin & Harvey is delighted to be working with East Dunbartonshire Council to deliver Allander Leisure and Day Care Centre.

"From the commencement of this exciting project, we have been working in partnership with the Council and supporting the local community. It has been a really positive experience to date and we will continue to input into local projects, employment and skills throughout the duration of the project."

Latest Construction News

15/11/2024

A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024

Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024

The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024

Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024

Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit.  The ambitious project will involve a range of ...
15/11/2024

The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024

Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024

Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024

The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024

BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...
RBT Underfloor LimitedMorris & Spottiswood LtdPerthshire Joinery LtdK A Tree SurgerySuperior Exterior CleaningIBT Building & Timber (Merchants) LtdLionheart RoofingRamsay & Sons [Forfar] LtdSynergy Lifting SolutionsSynergy Training Solutions
Terms and Conditions
2024/11/16 06:31:27