Leith Walk in Edinburgh is to reopen to two-way traffic between Pilrig Street and London Road from Monday, 18 July.
The main construction works between Montgomery Street/Annandale Street and Pilrig Street have been completed and fencing will be removed from outside businesses and homes.
The Trams to Newhaven project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction anticipated to be complete by the end of 2022 ahead of a testing and commissioning period.
Progress to date includes:
• Almost 3,900 metres of track laid, 84% of the total
• Main construction works completed on three out of the eight new tram stops with works progressing well at the Balfour Street, Foot of the Walk and Newhaven stops
• Over 4,000 metres of communications ducting installed (87% of the total) serving the tram and future communication requirements in the area
• More than 4,000 metres of drainage installed (89% of the total)
• Over 60,000 deliveries from the logistic hubs to local businesses
• Almost 24,500 itison vouchers sold, generating over £240,000 potential spend in participating businesses on the route.
• Over £175,000 spend on open for business campaigns
• Main construction works complete on several sections, including Ocean Terminal to Rennie's Isle and between Tower Street and Constitution Place and Tower Street and Baltic Street.
However, the programme for some specific sections of the route has changed due to industry wide challenges with the availability of materials and skilled labour, as well as other issues including complex utility conflicts.
As a result, some stretches are scheduled to take longer than originally planned, including Melrose Drive and outside Ocean Terminal. Full details of the updated programme are available on the Trams to Newhaven website.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...