Transformer Units Delivered To Abernethy Project

Construction News Image
Two new transformer units have been successfully delivered to an ongoing substation extension project in Abernethy in Perthshire.

The new 120 MVA transformer units, each weighing around 100 tonnes, are key components in the ongoing development of the substation extension and will replace the existing infrastructure at the site, playing a major role in increasing electricity capacity at the substation and helping to transport clean renewable energy generated in the area.

Teams from SSEN Transmission and principal contractor Freedom Group have been working since construction began in October last year to deliver the substation extension, which once complete will allow for the connection of new renewable electricity to the local electricity distribution network.

So far teams have completed the new platform extension and installed the new internals roads which allowed the transformers to be delivered adjacent to the newly created bunds. High-voltage cable installation and ducting for both circuits is also nearing completion.

The two transformers were manufactured by SGB in Germany and delivered to site by J B Rawcliffes under Police escort from Immingham Docks near Hull. Contractor ROSH are currently installing the transformers on behalf of SGB, with installation of the first transformer nearing completion. The second is expected to be commissioned in September.

-- Advertisement --
NorthernAsbestosServicesLtd

Teams are now working on further electrical work to install the remaining busbar and cable components on site. Following the successful commissioning of the new substation extension, the old plant will be removed and recycled in stages.

To help mitigate the visual impact of the new extension and improve biodiversity at the site, teams will extend the existing tree line around the substation and plant a variety of native trees to help screen it from view. Bunds are also being built along the edge of the development next to the local U75 road, which will be planted with native species of hedgerows and trees to help improve the natural wildlife as well as reduce the visual impact. SSEN Transmission is committed to delivering biodiversity net gain for all projects by 2025, and the planting of native species around the site will help contribute to a sustainable site which is rich in wildlife.

SSEN Transmission Project Manager Ewan Macfarlane said: "The Abernethy Substation Extension project is moving at pace now that the two transformer units have safely arrived at their final location.

"We have been coordinating and planning for their safe delivery since the earliest stages of developing plans for the new substation extension, so we’re pleased that they arrived here safely and worked to ensure we kept disruption to a minimum for the local community and road users.

"With the transformers now onsite and most of the primary plant now installed, we are well on track for the new substation extension to be complete and operational by March next year.

"We thank the local community and stakeholders for their continued patience while we work to complete the Abernethy Substation Extension, and will continue to keep them updated as we progress."

The Abernethy Substation Extension project involves constructing an extension to the existing electricity substation in Abernethy, allowing for future connection and onward transportation of clean renewable energy generated in the area.

Latest Construction News

15/11/2024

A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024

Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024

The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024

Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024

Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit.  The ambitious project will involve a range of ...
15/11/2024

The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024

Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024

Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024

The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024

BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...
Morris & Spottiswood LtdRBT Underfloor LimitedA.G.S Steel Erectors LtdRBT Underfloor LimitedJGasJohnston Oils LimitedThe Big Block Co LtdFour Seasons Scotland Design & Build LtdEuro-Fab (Scotland)Gas Call Services Ltd
Terms and Conditions
2024/11/16 06:48:08