The new tram track in the Newhaven district of Edinburgh is taking shape ahead of its scheduled launch next year.
Two final concrete pours will take take place this week at Rennie's Isle and Melrose Drive. The Rennie's Isle pour will be the longest on the project (170m) and once completed track will be laid from Picardy Place to Newhaven, leaving only a small section at York Place to link the existing line with the new track.
To date, 4.5km (96%) of track has been laid, with tram track now running continuously from Picardy Place to Tower Place, 100% of utility diversions have been completed and major civil works are finished on five of the eight new tram stops.
Energisation of newly installed overhead lines during November and December will allow a testing and commissioning period to begin at the start of 2023.
Councillor Scott Arthur, Transport and Environment Convener, said: "Both the electrification of overhead lines along the entire Trams to Newhaven route and final concrete pours are major milestones for this important Council project, and signal the final touches being made before we see trams on Leith Walk and beyond.
"A great deal of work has gone into reaching this stage, as progress on tracklaying, completed sections and other elements shows. That the project is still on schedule for delivery on time and in budget is thanks to the efforts of the entire team involved, who have had to contend with a Covid-related site shutdown and industry-wide labour and material challenges over the last three years.
"Of course, I'm also appreciative of local residents and businesses for their patience during this time. I'm confident that the finished scheme will be extremely beneficial to the community, transforming the streetscape, boosting the economy and proving reliable, sustainable journeys to and from the city centre."
Maria Ortega, Sacyr Farrans Neopul (SFN), Project Director on Edinburgh Trams York Place to Newhaven, added: "As contractors on the Trams to Newhaven project we are excited to be reaching these key milestones which are critical to ensuring the delivery of the Edinburgh Trams to Newhaven Line. Our efforts are firmly focused on ensuring that we continue to work in a safe and timely manner to deliver a high-quality end product.
"As contractors, SFN has brought extensive experience in the light rail sector to this project. Despite the challenges of unprecedented times that we have experienced throughout the life cycle of the project we are proud of the progress we have made by working successfully alongside our partners, supply chain and client."
The Trams to Newhaven project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction anticipated to be complete by the end of 2022 ahead of the testing and commissioning period.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...