Network Rail has completed the installation of 121 new overhead electrification structures as part of the wider project to upgrade and remodel Carstairs Junction.
This is part of a phased programme of investment in the key junction on the West Coast Main Line which will simplify and upgrade the track-layout to clear an existing bottleneck on the network and enable the separation of non-stop passenger and freight trains from those stopping at the station.
Work to date at Carstairs represents an investment of more than £100m in the junction to rationalise and simplify the track layout and modernise the signalling through one of the most critical sections of the Scottish rail network.
The installation of new sections of track and modern signalling will also speed up journeys between Glasgow and Edinburgh and will accommodate the longest freight trains on our network.
Over the last 18 months teams from industry partners Siemens, Rail Systems Alliance and SPL Powerlines have been carrying out heavy engineering on the railway embankments through the junction, as well as installing the new overhead line masts and signalling system.
Despite being largely restricted to Saturday nights, the project has already delivered more than 3km of track renewals and 1.5km of drainage, installed the new structures, and started the process of removing some of the redundant equipment.
Much of the equipment through the area is nearing the end of its operational life-span and the layout of the junction is no longer suited to the needs of today's railway in terms of supporting the pattern and volumes of service.
Extensive renewal and simplification of the layout was seen as the best long-term solution to deliver the reliable and resilient network needed at this key junction.
The next phase of work in 2023 will see the addition of another 4km of new drainage, further embankment work and will complete the installation of 10km of new track to create a faster, more flexible and more easily maintained layout.
Jim McCleary, programme manager at Network Rail said: "We're now gearing up for the final construction of the new track layout, which includes 10 kilometres of track and 27 new sets of switches and crossings, which allow trains to move between tracks.
"One of the main challenges on the project is the integration of the different teams working on site given the sheer volume of activity happening within the limited work window that we have on Saturday nights.
"Access to the railway at this critical junction is very limited, but the team has worked hard with the wider industry to balance the needs of train operators with the longer-term benefits that will come from modernising the track, signalling and overhead line equipment."
Carstairs junction sits 26 miles to the South-East of Glasgow on the West Coast Main Line. The triangular junction provides a route between Glasgow & Edinburgh and both Glasgow and Edinburgh to the south.
More than 200 services pass through the junction on an average midweek day with 12 train and freight operators regularly using the route. The Caledonian Sleeper Lowlander service splits and joins in this location both morning and night for Glasgow and Edinburgh for Euston services.
Time and date
CONSTRUCTION DIRECTORY
Construction News
31/10/2022
Network Rail Completes Overhead Electrification Structures Installation
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...