SSE Renewables has identified an increase in the potential project capacity from 2.6GW to up to 3.6GW for the proposed Ossian Wind Farm off the East Coast of Scotland, which if achieved, would put it among the top five largest floating offshore wind farms globally.
The Ossian project is being delivered by a partnership of leading Scottish renewable energy developer, SSE Renewables, Japanese conglomerate Marubeni Corporation (Marubeni) and Danish fund management company Copenhagen Infrastructure Partners (CIP).
In recent months the Ossian project completed a full geophysical and benthic survey of the project area. The data collected has informed a review of the potential wind farm capacity. Subject to undertaking the necessary further environmental and technical assessments, the site could be used to generate the increased capacity of up to 3.6GW.
David Willson, Senior Project Manager For Ossian, said: "We are excited that through further technical assessment of our project area, we now believe Ossian could provide an even greater renewable electricity output. If realised, this change would position the project among the top five largest floating projects in the world, demonstrating its epic scale. This is a great motivator for project partners SSE Renewables, Marubeni and CIP and the whole project team."
David continued: "Our geophysical survey collected data to a very high standard, ahead of schedule and under budget in 109 days with zero HSE incidents – an amazing achievement to be proud of.
"Our FLiDAR and Metocean measurement campaign successfully kicked-off in August which will deliver comprehensive measurements of the metocean conditions to inform the development of the Ossian site.
"We will now work with our stakeholders and regulators to secure the appropriate consent so that the full potential of the Ossian Wind Farm Project can be realised."
Floating LiDAR (or FLiDAR: Floating Light Detection and Ranging) equipment is now acquiring data at the Ossian site having been deployed by Glasgow-based metocean specialists PARTRAC.
The company has placed EOLOS FLS 200 FLiDAR equipment across two locations at the Ossian site with the aim of measuring wind speed and direction to help determine the best locations and positions for wind turbines.
PARTRAC have also deployed their metocean equipment consisting of three wave buoys and three subsea moorings at three locations. The installed equipment will measure the waves, current, tidal levels, turbidity, conductivity, and temperature.
Sam Athey Managing Director From PARTRAC, said: "Our work at the Ossian site marks the start of two years of data collection so that we can build knowledge of site characteristics and capture critical metocean data. This is an incredibly important process as it establishes both the wind resource and environmental conditions for the project. We're very pleased and proud to be involved in this flagship project."
The proposed floating offshore wind farm takes its name Ossian (pronounced 'os-si-un') from The Poems of Ossian. It is set to be located across 858 km2 of seabed in waters off the east coast of Scotland. The deployment of floating offshore wind turbines delivering up to 3.6GW of new installed capacity is enough to be capable of powering almost 6 million Scottish homes and offsetting around 7.5 million tonnes of harmful carbon emissions each year.
When complete, the project will be amongst the world's largest floating offshore wind farms, positioning Scotland as a global leader in floating offshore wind technology. The Ossian team will be holding scoping workshops with key stakeholders on week commencing November 14th to help better understand their initial views.
Time and date
CONSTRUCTION DIRECTORY
Construction News
04/11/2022
Increase Capacity Identified At Ossian Wind Farm Development
Latest Construction News
29/11/2024
Construction has begun on the initial phase of Spaceport 1, a sub-orbital launch site in the Outer Hebrides. Local contractor, Macaulay Askernish Ltd, has been awarded a contract by Comhairle nan Eilean Siar to undertake enabling works at Scolpaig Farm in North Uist. The project, funded by a £947k ...
29/11/2024
David Smith Contractors Ltd, a local firm based in Fraserburgh, has been awarded a multi-million-pound contract to contribute to the construction of the Eastern Green Link 2 (EGL2) project. The company will undertake civil engineering works at the converter station site near Boddam, Peterhead. ...
29/11/2024
Scotland has unveiled a new plan to become a leading exporter of renewable hydrogen by 2030. The plan, titled 'A Trading Nation: Realising Scotland's Hydrogen Potential – A Plan for Exports', outlines specific actions needed to achieve this goal. The Scottish Government aims to capitalize on the ...
29/11/2024
First Minister John Swinney has welcomed the progress being made in the construction of the new Perth High School during a recent site visit. The new three-storey building, being delivered by Robertson Construction Tayside on behalf of hub East Central Scotland, will accommodate up to 1,600 pupils ...
29/11/2024
Glasgow City Council has given the green light to the sale of four land plots in the city to facilitate various development projects. The sites in question are located in Carmyle, Deaconsbank, Maryhill, and Port Dundas. The disposals are expected to generate significant capital receipts for the ...
29/11/2024
Scottish Water is set to achieve a significant milestone in its woodland creation programme, planting over 500,000 trees by the end of the current planting season in March 2025. This year, the company will plant more than 245 hectares of native woodland across various sites, including Loch ...
28/11/2024
Construction has begun on a new £33 million student accommodation development in Glasgow city centre. The project, a partnership between Artisan Real Estate and Homes for Students, will provide 321 self-contained studio apartments at 292-298 St Vincent Street. The existing office building on the ...
28/11/2024
Springfield Properties has submitted detailed plans to Midlothian Council for the first phase of its new Lingerwood development. The proposed development, located off Stobhill Road near Newtongrange, will eventually include around 1,000 homes. The first phase will comprise 63 homes, ranging from ...
28/11/2024
Scottish Land & Estates (SLE) has called on the Scottish Government to prioritise the needs of rural communities in the upcoming Scottish Budget. Dee Ward, Chair of SLE, has urged the Finance Secretary, Shona Robison, to conduct a robust rural impact assessment for all spending and taxation ...
28/11/2024
Four Scottish electrical apprentices have been praised for their performance in the prestigious SkillELECTRIC competition. John-Ross Campbell, Kalum Low, Milly Smith, and Ewan Thomas, all SETCTT apprentices, represented Scotland in the UK-wide competition, which was held at Oldham College. Milly ...