14/12/2022

Loch Lochy Pumped Storage Scheme Exploratory Works Underway

Construction News Image
Exploratory works at the site of what would be the UK's first large-scale pumped storage scheme to be developed in 30 years have commenced at Loch Lochy in the Great Glen in the Scottish Highlands.

SSE Renewables selected Strabag UK, a world leader in mining and tunnelling projects, to undertake the work earlier this year. The company which has extensive experience in complex infrastructure and ground engineering, was named the preferred tenderer to carry out the work after a rigorous selection process which concluded in April.

The work will see the creation of a tunnel approximately four metres wide and up to one kilometre long, which will cut into the hillside towards the proposed location of the underground powerhouse complex.

Samples of the materials within the hill will be analysed, and survey and assessment work will be carried out to give a detailed understanding of the geological conditions. The information will then be used in detailed design of underground structures.

-- Advertisement --
NorthernAsbestosServicesLtd

The findings of the exploratory works will be used to inform the final design of the project and will be an important consideration in SSE Renewables' final decision on whether to proceed with the Coire Glas project.

Ian Innes, Project Director For Coire Glas, said: "Coire Glas is one of the most significant engineering projects to take place in the UK for decades. The commencement of these exploratory works is a great milestone for everyone on the Coire Glas Project Team and at SSE Renewables.

"With a reputation for innovation and delivering a wide variety of specialist skills and services on major construction projects, I am confident that Strabag UK's experience will prove an asset as we undertake this critical phase in the development of the Coire Glas project."

In November 2021, SSE Renewables' parent company, SSE PLC unveiled its Net Zero Acceleration Programme, or NZAP, which commits to investing around £7m a day on critical low-carbon infrastructure needed in net zero transition.

Major infrastructure projects including Coire Glas are at the heart of the NZAP with a target to double our installed capacity by 2026 and more than treble it by 2031, increasing output fivefold to over 50TWh annually. The fully funded NZAP will see 40% of the £12.5bn capex spent in SSE Renewables.

Latest Construction News

15/11/2024

A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024

Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024

The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024

Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024

Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit.  The ambitious project will involve a range of ...
15/11/2024

The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024

Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024

Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024

The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024

BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...
RBT Underfloor LimitedMorris & Spottiswood LtdJSJ Foam Insulation LtdEarth Tech LPS LTDSolway Ecology Consulting LtdPerfect View Aerial FilmingBurnside Plant Hire LtdSips Eco Panel Systems LtdM K M Building Supplies LtdAlternative Tying Systems Ltd
Terms and Conditions
2024/11/16 06:52:21