Build Scotland Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
22/12/2022

Noss Head Switching Station Project 'Striding Forwards'

Construction News Image
SSEN Transmission has announced that construction of the new Noss Head Switching Station project, which will form a key part of the Shetland HVDC Link, is "striding forwards" with the main building exterior now complete.

The new switching station will serve as a key component in the 260km subsea cable project between Shetland and the mainland, which will involve connecting the island to the main national grid for the first time.

The 125m long building will house the electrical components used in the Shetland HVDC link, which will allow the flow of electricity to be managed between three underground HVDC circuits - one from a converter station at Spittal in Caithness, one from a converter station at Kergord in Shetland and one to a converter station at Blackhillock in Moray. A spare connection bay has also been installed for future circuit connections.

The system will connect to the existing HVDC system between Caithness and Moray, making use of capacity available in the Caithness-Moray subsea cable to allow onward connection to the existing onshore transmission network in Moray and beyond with minimum new infrastructure.

All road surfacing has also been completed to ensure safe, smooth access to the infrastructure.

With the main construction of the building complete, Hitachi Energy has now begun work to install their specialist equipment within the switching hall, which is making good progress. 

Cable pulling is underway in the switching hall for the control and protection of the electrical equipment, with work expected to be completed by the end of the year.

-- Advertisement --
NorthernAsbestosServicesLtd

The commissioning process where all subsystems will be integrated and tested is underway and is expected to continue into early 2023 in preparation for the first outage in 2023, which will see the first cables of the Caithness-Moray link connected into the Noss Head Switching Station.

Landscaping bunds have been constructed around the building to help screen the development and lessen the visual impact of the new building. Since their development, over 20,000 native species of trees and shrubs have been planted on and around these areas, with a further 15,000 to be planted once the site is cleared and office areas removed. Native wildflowers have also been seeded around the site to help encourage biodiversity by attracting insect and bird species to the area.

Since construction began in January 2021, the team have been working closely with the local community to help keep them informed as the project develops, as well as to provide support on community initiatives where they can. Most recently, the team from SSEN Transmission along with their principal contractor BAM Nuttall and principal cable contractor NKT contributed towards the cost of activities for Wick Highlife Highland schools out programme, which supported over 200 young people with different sports activities during the school holidays in October. The teams also covered the cost of sports programmes during the summer months, which benefitted over 550 young people during the school holidays. The project team has also made donations to Caithness Foodbank, restored over 900m of footpath around Wick, as well as helped install new colourful lighting around the riverside fountain in Wick, at the request of Wick Community Council and Wick Paths Group.

Martin Baker, SSEN Transmission Project Manager said: "We're really pleased that construction of the Noss Head Switching Station building is complete, marking another major milestone in the Shetland HVDC link project.

"This means that teams from Hitachi Energy can now progress with work to develop the electrical infrastructure inside, which will ultimately control the flow of electricity from the different HVDC routes and play a vital role in the overall development.

"Working with the community is something that has been really important to us since before construction even started, and we're really pleased that ourselves and BAM Nuttall have been able to continue to support a number of brilliant local initiatives, most recently covering the cost for over 750 young people to enjoy sport activities during the October and summer school holidays.

"A huge credit to the teams and BAM Nuttall for all the hard work in reaching this stage, and we look forward to building on the good progress made so far as we continue to develop the Noss Head Switching Station."

Latest Construction News

15/11/2024

A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024

Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024

The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024

Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024

Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit.  The ambitious project will involve a range of ...
15/11/2024

The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024

Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024

Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024

The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024

BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...
RBT Underfloor LimitedMorris & Spottiswood LtdToner Damp Proofing SuppliesNo HydroSEEIT3DCF Concrete PumpingMaccaferri LtdSMS Alba LimitedDiscount Kitchens and Bathrooms LtdShopfronts Scotland
Terms and Conditions
2024/11/16 06:58:02