Trams To Newhaven Project Enters Final Testing Stage

Construction News Image
The first tram has run down Leith Walk in Edinburgh in over 65 years as official testing got underway in the final stages of the Trams to Newhaven project.

Ahead of the route opening for service in spring 2023, a period of testing and commissioning is required to ensure the newly constructed line, software and signals work effectively and safely.

On Monday (13 March), the first stage of testing began, which involves trams travelling at walking pace along small sections of the route, starting at Picardy Place. This will continue through the week, taking place during the night to minimise traffic disruption.

Once the first stage is completed, the frequency and speed of tram testing will increase, and trams will start running to a timetable. Drivers on the route have carried out significant training in the lead-up to testing, including on a state-of-the-art simulator. People are still being encouraged to take care and be aware of the presence of trams on the route for the first time over the coming weeks.

Councillor Scott Arthur, Transport and Environment Convener, said: "This is a huge milestone for Trams to Newhaven as we see the first trams on Leith Walk in my lifetime. We’re fast approaching the start of passenger services this spring, and that the project is set to be delivered on time and within budget, despite the challenges of recent years, is testament to the hard work of all those involved.

-- Advertisement --
NorthernAsbestosServicesLtd

"Bringing the tram to Newhaven will be transformative for the area, and the wider city. As well as boosting the economy and providing sustainable, high-capacity public transport to this densely populated part of Edinburgh, the project has significantly improved the entire route, with new cycle links, spaces to relax and spend time and newly planted trees and shrubs.

"As we enter the final phase of the project, testing and commissioning will make sure the line and infrastructure works safely and efficiently, while also confirming service capacity. Of course, this is the first time there will be trams on Leith Walk and in Leith in recent years so I would urge people to take extra care when in the area."

Lea Harrison, Managing Director of Edinburgh Trams, said: "To see one of our trams running along Leith Walk was a proud moment for us, and this latest milestone in the project will enable us to step up our own preparations for the launch of passenger services to Newhaven.

"This includes real-world driver training on the new section of line following an intense period of familiarisation involving our state-of-the-art tram simulator."

The Trams to Newhaven project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction now complete. A specific date for when the route will be open for passengers will be announced in due course.

As part of the commissioning process every aspect of the new infrastructure will be thoroughly tested to ensure it meets the required safety standards.

There will be some bus diversions around Leith Walk in place overnight during the week commencing 13 March to allow for the testing. The latest information on diversions is available on the Lothian Buses website.

Due to industry wide challenges with the availability of materials and skilled labour, impacted by Brexit and the war in Ukraine along with significant demand for labour in the UK and overseas, there are small pockets of public realm works that will now be completed over the coming months.

Latest Construction News

15/11/2024

A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024

Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024

The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024

Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024

Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit.  The ambitious project will involve a range of ...
15/11/2024

The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024

Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024

Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024

The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024

BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...
RBT Underfloor LimitedMorris & Spottiswood LtdAC Cable Solutions24-7 HealthcareThe Scottish Natural Insulation HubPD ServicesACCON UK LtdToner Damp Proofing SuppliesNo HydroSEEIT3D
Terms and Conditions
2024/11/16 06:25:34