Network Rail has announced the successful completion of engineering works at Carstairs Station.
During a 12-week phased closure, Network Rail worked around the clock to deliver the extensive investment in the critical West Coast Main Line (WCML) junction which included remodelling and upgrading the platforms at the South Lanarkshire station.
As part of the work to remodel the junction, engineers have realigned the station platforms to work with the new track geometry and overhead wire layout. This included reshaping 65m at the south end of platform 1 to enable a more efficient connection from the station to the Edinburgh line.
Work also saw the removal of the platform edges and surfaces and the renewal of more than 300m of platform surface drainage. The lighting systems across the station were also upgraded before new platform copes, with integrated tactile edges, were added and the full 2,500 square metres of the platform was resurfaced.
Jim McCleary, Network Rail's programme manager for the Carstairs project said: "While part of the work was essential to the overall delivery of the remodelling of the junction, the track-access provided an opportunity to renew and upgrade the platforms at the station.
"The station work was delivered during the 12-week closure on the line and I am delighted that this was carried out safely and efficiently. It's credit to the skill and expertise of the contractors involved.
"Thank you to passengers for their patience during this work. I hope that they begin to see and experience the benefits the investment in the railway is delivering."
David Simpson, ScotRail Service Delivery Director, said: "We are delighted that the work at Carstairs has been completed successfully and the station can now reopen for passenger service.
"We know lengthy line closures can be a real inconvenience for customers, and while we do everything we can to keep people moving during major upgrade works, it's great to get people back to travelling on trains.
"I'd also like to thank our customers for their patience while this important work to both the junction and station was delivered."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...