Build Scotland Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
14/06/2023

New Port Ann To Crossaig Overhead Line Project Energised

Construction News Image
With the successful completion of works to install over 500km of conductor cable, 9,500 cubic metres of concrete, almost 3,000 tonnes of steel over the course of some 500,000 working hours, the new Port Ann to Crossaig overhead line project has been energised.

Stretching from Port Ann substation near Lochgilphead to the substation at Crossaig, the new overhead line developed by SSEN Transmission and their Principal Contractor Balfour Beatty is around 45km in length. Supported on 148 newly installed steel-lattice towers, the new line has been designed to be more resilient in extreme weather events, enhancing the security of supply for those living and working in the area.

This is the first major project to be energised under SSEN Transmission's RIIO T2 Framework, marking a major milestone in their wider strategy to deliver a network for net zero emissions across the north of Scotland.

The new line has been built to replace the existing 132kV line, originally built in the 1950s, which has reached the end of its operational life. SSEN Transmission has future proofed the new overhead line by building it to initially operate at 132kV with the capacity increase to 275kV, meaning it can accommodate future contracted electricity generation on to the grid.

Following on from energisation of the new overhead line, the existing 132kV line will be decommissioned and carefully removed from the landscape. This work is expected to be completed by the end of 2023.

During peak construction, around 150 people worked on the new overhead line between Port Ann to Crossaig, with over half-a-million working hours spent delivering the project across SSEN Transmission and its contractors.

The Port Ann to Crossaig project is the second phase in the wider Inveraray to Crossaig powerline upgrade, with the first phase – Inveraray to Port Ann – energised in July 2021. The replacement line, which stretches a total of 84km across both phases, serves as the main arterial route for electricity transmission in Argyll, keeping the lights on for homes and businesses throughout the Peninsula.

Building a project of this size has brought significant benefit to the local economy. Teams across both Phase 1 and 2 of the Inveraray to Crossaig project have contributed significantly to the £7 million spent by SSEN Transmission and their contractors on food and accommodation in the Argyll and Bute Council area since April 2020, including spending around 50,000 nights in local accommodation.

-- Advertisement --
NorthernAsbestosServicesLtd

As a stakeholder-led business, the team has worked to keep the community informed throughout the project via monthly community liaison groups to keep stakeholders up to date on progress. The team also carried out various volunteering initiatives to give something back to the area, which included projects such installing a new sandpit for outdoor nursery MAKI Pups, run by Argyll and the Isles Coast and Countryside Trust; painting the interior living-space of Ardfenaig Residential Home in Ardrishaig; and donating high-vis clothing and torches to Tarbert High School to help keep pupils safe on their commute to school during the winter months.

SSEN Transmission has committed to replanting over 270 hectares of trees which were removed during construction, and, where possible, opting for native tree species.   Last year, SSEN Transmission and leading community and conservation organisation Argyll and the Isles Coast and Countryside Trust (ACT), and Argyll and Bute Council joined forces to help deliver these tree planting commitments and in doing so, help support and enhance Scotland's rainforest in Argyll.

The ground-breaking partnership has already seen the initial phase of planting get underway on Argyll and Bute Council's sites near Lochgilphead, which once complete will see approximately 50,000 native trees planted. By planting native species, the planting will support local flora and fauna, creating natural habitats for native species to thrive, supporting SSEN Transmission's commitments to deliver biodiversity net gain and compensatory planting on all its major projects.

The planting will also create a natural asset for the local community to enjoy for generations to come, leaving a positive lasting legacy beyond SSEN Transmission's primary objective of delivering a network for net zero emissions across the north of Scotland.

SSEN Transmission Project Manager Peter Brum, said: 

"Energising the line is a hugely significant milestone in the Port Ann to Crossaig project, and I'm delighted that after 24 months of hard work from across our teams and contractors Balfour Beatty and Scottish Woodlands, the new line is now live.

"The Port Ann to Crossaig replacement line joins to form the full Inveraray to Crossaig overhead line, which is providing a more secure, reliable and safe means of transporting energy to homes and businesses right across Argyll. 

"Energising on schedule is a testament to everyone's hard work and dedication, in the often challenging working conditions brought by the Argyll weather and the remote locations of some parts of the line.  The team came together to deliver this project safely, and while this project hasn't been without its challenges, it is testament to the team's experience, professionalism and dedication that when faced with problems we have worked together to reach solutions.  As a project team we are proud of the role we are playing in delivering a network for net zero.

"We would like to thank the communities and land owners along the route for their support and continued patience throughout the build, without which the project and its role in reinforcing the transmission network in Argyll would not have been possible."

David Nevin, Balfour Beatty Senior Project Manager, said: "The successful energisation of the remaining circuits marks a momentous milestone for everyone involved from the Balfour Beatty and SSEN Transmission project teams. We are live and operational from Inveraray through to Crossaig. This upgrade secures the supply of energy to consumers in the Argyll & Bute Peninsula and supports the connection of increased renewable generation.

"We were exceptionally lucky to have had so many fantastic people support us in the delivery of the project. Everyone involved should be very proud of what we've achieved together in some of the most difficult and challenging terrain in the UK. This combined with a challenging programme all add to the sense of satisfaction upon successful energisation."

Teams are now turning to the remaining final phase of work, which involves taking down the previous overhead line and removing the old towers. This will be followed by reinstatement of construction areas and temporary access tracks, which will help restore areas temporarily used during the build.

Latest Construction News

15/11/2024

A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024

Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024

The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024

Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024

Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit.  The ambitious project will involve a range of ...
15/11/2024

The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024

Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024

Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024

The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024

BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...
Morris & Spottiswood LtdRBT Underfloor LimitedBurnside Plant Hire LtdSips Eco Panel Systems LtdM K M Building Supplies LtdAlternative Tying Systems LtdContainexPerthshire Joinery LtdK A Tree SurgerySuperior Exterior Cleaning
Terms and Conditions
2024/11/16 06:50:19