Scottish Water Completes Major Tunnel Works In Glasgow

Construction News Image
Scottish Water has announced the successful completion of a key part of a new trunk water main in Glasgow, beneath a motorway and railway, as part of a multi-million pound project to benefit almost one million customers.

A state-of-the-art tunnel boring machine, the hi0tech TBM, installed a 252 metre-long tunnel and section of water main from Broomloan Road in Ibrox, in the shadow of Ibrox Stadium, to the north side of Bellahouston Park.

The tunnel, which goes below the M8 motorway, Paisley Road West and the Glasgow-Ayr railway line, is part of more than seven miles of new water mains being installed in a project which will connect the Glasgow area's network and the system in Ayrshire to increase resilience and protect supplies for customers.

The TBM installed the tunnel at a depth of up to 20 metres below ground – the equivalent of the height of a seven-storey building – while thousands of road and rail users above went about their daily business undisturbed and largely unaware.

It excavated about 1,311 tonnes of rock, such as sandstone and mudstone which went to landfill, and installed a total of 100 sections of pre-cast concrete pipes each measuring 2.5 metres in length and taking the total weight of the tunnel to about 500 tonnes.

The work using the TBM in Ibrox is a key part of a project to improve Scottish Water's water mains network in the south west of Glasgow by installing new pipes which will connect the Glasgow area's network and the system in Ayrshire to improve the security of supply for customers.

Connecting the networks will provide a two-way water supply between the Milngavie Water Treatment Works (WTW) system, which provides water for more than 700,000 people across much of the Glasgow area, and the Bradan WTW system which supplies more than 200,000 customers across much of Ayrshire. It will also benefit almost 50,000 customers in East Renfrewshire.

In the event of a disruption to the water supply in either Ayrshire or Glasgow, the new system will allow millions of litres of water to be transferred in either direction, minimising the impact on customers if there is a burst main or other operational issues.

-- Advertisement --
NorthernAsbestosServicesLtd

The project, which involves the use of innovative construction materials and techniques to reduce carbon emissions and power requirements, is being delivered for Scottish Water by Caledonia Water Alliance, our alliance partner, and is expected to be completed in 2024.

The new water main is being installed in the Ibrox, Mosspark, Pollok, Priesthill, Nitshill and Parkhouse areas of Glasgow and will run from Ibrox to a reservoir storage tank in the Parkhouse/Darnley area.

A new pumping station is being built at Ibrox which will push water to the existing pumping station in Parkhouse/Darnley for onward distribution to Ayrshire.

The work in the south of Glasgow is the third and final stage of the overall investment which has already delivered improvements in Ayrshire.

The design of the new network incorporates carbon reducing construction materials and methods including innovative self-restraining pipe. Solar panels will also offset the power demands at the new Ibrox pumping station, with the new mains using gravity to reduce power use by 60%.

Four tunnels – one at Ibrox under the M8 motorway and the Glasgow-Ayr railway line, another under the Paisley Canal railway and White Cart Water, another under the Glasgow-Barrhead-Kilmarnock railway and one under the Levern Water will form part of the route of the new main.

The tunnels under the Glasgow-Barrhead-Kilmarnock railway and the Levern Water have already been completed.

The start of the construction of the tunnel at Ibrox, which is the biggest of the four and was carried out for CWA by HB Tunnelling Ltd of Doncaster, England, was witnessed by three pupils from Ibrox Primary School, located near the project, who took part in a competition to give the TBM a female name, in accordance with tunnelling tradition.

Primary five Ibrox Primary School pupil Manha Raheel won the competition and the TBM was named Tytana.

The hydraulically-operated TBM worked 24-7 and completed its breakthrough when the cutting head emerged at a point in Bellahouston Park. Manually operated by a driver at the front, the TBM's rotating cutting head cut into the earth and rock and the material was transported along a conveyor belt to a skip on the TBM before being removed by crane to the surface. 

A team of six people working on the tunnelling also included a supervisor and banksman.

After the tunnel was installed, 22 sections of water main made from ductile iron were placed inside it, using a crane to lower the pipe sections down and a winch to pull them through the tunnel and into position before they were grouted and sealed.

We liaised with Transport Scotland regularly during the tunnelling to ensure they were kept informed about its progress.

Dominic Flanagan, Scottish Water Delivery Manager, said: "The installation of this particular part of the new water main using the TBM is arguably the highlight of this project so far and we are delighted to have completed it.

"Everything went well with this very challenging and complex operation and we were really pleased that our guests from Ibrox Primary School FC were able to join us and see the tunnelling start."

He added: "Linking our supply systems in Glasgow and Ayrshire will ensure that high-quality drinking water can continue to be supplied to current customers and for generations to come.

"The investment in below-ground infrastructure will also support the continued development above ground in communities across these areas and will enable them to continue to grow and thrive."

Jane McKenzie, the project's Communications Manager, said: "From the very start of this project we have done everything possible to minimise any disruption for people like local schools, Rangers FC, local residents, and road users.

"We've done everything we can to keep them informed and hosting the schoolchildren on-site to see the start of this piece of tunnelling was one of our ways of thanking them for their patience and understanding and was, we hope, an interesting and enjoyable experience for them. We know that they too will be pleased to learn of the TBM breakthrough and completion of this key stage of our work."

Latest Construction News

29/11/2024

Construction has begun on the initial phase of Spaceport 1, a sub-orbital launch site in the Outer Hebrides. Local contractor, Macaulay Askernish Ltd, has been awarded a contract by Comhairle nan Eilean Siar to undertake enabling works at Scolpaig Farm in North Uist. The project, funded by a £947k ...
29/11/2024

David Smith Contractors Ltd, a local firm based in Fraserburgh, has been awarded a multi-million-pound contract to contribute to the construction of the Eastern Green Link 2 (EGL2) project. The company will undertake civil engineering works at the converter station site near Boddam, Peterhead. ...
29/11/2024

Scotland has unveiled a new plan to become a leading exporter of renewable hydrogen by 2030. The plan, titled 'A Trading Nation: Realising Scotland's Hydrogen Potential – A Plan for Exports', outlines specific actions needed to achieve this goal. The Scottish Government aims to capitalize on the ...
29/11/2024

First Minister John Swinney has welcomed the progress being made in the construction of the new Perth High School during a recent site visit. The new three-storey building, being delivered by Robertson Construction Tayside on behalf of hub East Central Scotland, will accommodate up to 1,600 pupils ...
29/11/2024

Glasgow City Council has given the green light to the sale of four land plots in the city to facilitate various development projects. The sites in question are located in Carmyle, Deaconsbank, Maryhill, and Port Dundas. The disposals are expected to generate significant capital receipts for the ...
29/11/2024

Scottish Water is set to achieve a significant milestone in its woodland creation programme, planting over 500,000 trees by the end of the current planting season in March 2025. This year, the company will plant more than 245 hectares of native woodland across various sites, including Loch ...
28/11/2024

Construction has begun on a new £33 million student accommodation development in Glasgow city centre. The project, a partnership between Artisan Real Estate and Homes for Students, will provide 321 self-contained studio apartments at 292-298 St Vincent Street. The existing office building on the ...
28/11/2024

Springfield Properties has submitted detailed plans to Midlothian Council for the first phase of its new Lingerwood development. The proposed development, located off Stobhill Road near Newtongrange, will eventually include around 1,000 homes. The first phase will comprise 63 homes, ranging from ...
28/11/2024

Scottish Land & Estates (SLE) has called on the Scottish Government to prioritise the needs of rural communities in the upcoming Scottish Budget. Dee Ward, Chair of SLE, has urged the Finance Secretary, Shona Robison, to conduct a robust rural impact assessment for all spending and taxation ...
28/11/2024

Four Scottish electrical apprentices have been praised for their performance in the prestigious SkillELECTRIC competition. John-Ross Campbell, Kalum Low, Milly Smith, and Ewan Thomas, all SETCTT apprentices, represented Scotland in the UK-wide competition, which was held at Oldham College. Milly ...
RBT Underfloor LimitedMorris & Spottiswood LtdToner Damp Proofing SuppliesNo HydroSEEIT3DCF Concrete PumpingMaccaferri LtdDiscount Kitchens and Bathrooms LtdShopfronts ScotlandJSJ Foam Insulation Ltd
Terms and Conditions
2024/11/30 00:17:28