Network Rail has announced a nine day programme of essential upgrade works for the West Highland Line between Crianlarich and Fort William/Mallaig.
The essential upgrade works will take place at Rannoch viaduct, just north of Rannoch station, as part of a £1.6m investment to extend the operational lifespan of the structure.
New timbers will be installed and the metal girders will be repaired, cleaned and repainted on the viaduct, which carries the line across the world-famous Rannoch Moor.
Engineers will work around the clock from March 16 to complete the project before the line reopens for service on Monday 25 March.
While the work is ongoing, services between Glasgow Queen Street and Fort William/Mallaig will be impacted with buses replacing trains between Crianlarich and Fort William and between Fort William and Mallaig.
Buses will also replace trains from Tulloch, Roy Bridge & Spean Bridge stations to Fort William but there will be no services to Rannoch and Corrour during the closure.
Services between Glasgow Queen Street and Oban will operate as normal throughout the closure.
Zoe Monkhouse, Network Rail's project manager for the Rannoch viaduct project, said: "The work we are undertaking in March is essential and cannot be delivered without closing the railway.
"We know that closing the railway at any time is never ideal, however we always endeavour to plan our work for when fewer people are travelling on the railway and at a time which reduces overall inconvenience for the travelling public.
"We understand that this is not great news for those making plans to travel to visit family or friends or for leisure purposes, but our team will be working around the clock to deliver these works safely and on time.
"We thank passengers for their patience and understanding and apologise for any inconvenience this may cause."
Phil Campbell, ScotRail Customer Operations Director, said: "We know the impact this line closure will have on customers, and we will be doing everything we can to keep people moving during the work.
"Replacement buses will be in operation, but journey times will take longer, and we encourage customers to check before they travel using the ScotRail website, app, or social media channels."
In addition to the work on the viaduct, Network Rail will also improve multiple sections of track between Tyndrum and Roy Bridge and between Spean Bridge and Arisaig.
Signalling upgrades will take place between Fort William and Spean Bridge and drainage enhancements will go ahead south of Rannoch station.
The works at Rannoch viaduct will involve replacing 50 longitudinal timbers (way beams), which run the length of the 208m structure and support the rail going over the steel bridge. The softwood timbers are life-expired and will be replaced with hardwood alternatives, with the existing baseplates and rail also being renewed.
These are part of ongoing efforts to enhance the safety and reliability of the railway for years to come.
If you have any questions about this work, you can contact Network Rail's 24-hour national helpline on 03457 11 41 41. For the latest information and progress updates follow on Twitter @NetworkRailScot.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...