The Glasgow Airport Rail Link (GARL) project has taken a major step forward with the completion of a seven-month long project to replace overhead power line equipment on part of the existing two-track line between Glasgow and Paisley.
Overhead power lines have been transferred to new supports, while redundant structures have been removed between Gower Street in Glasgow and the Arkleston area of Paisley.
This will allow construction of a new third line throughout this section which is required to increase capacity for the Glasgow Airport Rail Link and the Ayrshire and Inverclyde services.
The work has been undertaken by Network Rail on behalf of Transport Scotland; the Scottish Government’s transport agency charged with delivering the GARL project. The activity will help with subsequent work to install new infrastructure crucial to GARL.
The first phase of the work in this area took place between July and November 2007, when Network Rail installed new portal frames for the overhead line equipment, and work was completed between August 2008 and March 2009.
Nadia Savage, Transport Scotland’s GARL project director said: "Our delivery partner Network Rail has completed this phase of work which represents an important piece of the project which will eventually see passenger services to and from Glasgow Airport beginning in advance of the Commonwealth Games in 2014.
"In addition the project is paving the way for significant improvements to Ayrshire and Inverclyde services in advance of the new fleet of 38 eco-friendly electric trains being launched to the west of Scotland by the Scottish Government in September 2010."
Ron McAulay, Network Rail director Scotland, added: "We are pleased to have delivered this element of the project on time and look forward to continuing to play our part in making this much-anticipated rail link a reality for the travelling public."
The news follows the announcement that four separate bidders comprising seven of Europe's biggest construction companies will be invited to bid to build the branch line and viaduct which will cross the M8 and take passengers to the new airport station.
(GK/JM)
Time and date
CONSTRUCTION DIRECTORY
Construction News
22/05/2009
GARL Preparatory Work On Track As Overhead Line Expansion Complete
Latest Construction News
15/11/2024
A major milestone has been reached in the UK's transition to a greener energy future. Ofgem has approved the Eastern Green Link 1 project, a £2.5 billion investment that will see the installation of a 196km subsea electricity cable between Scotland and England. The project, a joint venture between ...
15/11/2024
Falkirk Council has secured a £100 million Growth Deal that is expected to create 1,660 jobs and generate £628 million in economic benefits for the area. The Deal, signed by the UK and Scottish Governments, will fund 11 projects, including: • A Carbon Dioxide Utilisation Centre • A Bioeconomy ...
15/11/2024
The Scottish Plant Owners Association (SPOA) has raised concerns that the measures announced in the Autumn Budget could lead to the demise of the plant hire industry in Scotland. The association argues that the increased tax burden and other economic pressures will have a significant negative ...
15/11/2024
Maxi Construction has been awarded a £1.6 million contract by The City of Edinburgh Council to replace the Reinforced Autoclaved Aerated Concrete (RAAC) roof at Pentland Primary School. The phased project will involve the removal of existing roof coverings and ceilings, the replacement of RAAC ...
15/11/2024
Clark Contracts has been awarded a contract to retrofit Scotland's National Retrofit Centre at BE-ST's Innovation Campus. The project aims to transform the building into a living laboratory, showcasing best practices in non-domestic retrofit. The ambitious project will involve a range of ...
15/11/2024
The Scottish Government has announced plans to bypass the villages of Springholm and Crocketford on the A75, a key route linking Scotland to Ireland. Jacobs UK Ltd has been awarded a contract to undertake initial design and assessment work for the bypass. The project is funded by the UK ...
15/11/2024
Dundee City Council has secured a £693,383 grant from the Scottish Government's Recycling Improvement Fund to upgrade its recycling facilities at Baldovie and Riverside. The funding will be used to purchase new waste management equipment, such as roll packers and compactors, to improve efficiency ...
15/11/2024
Homes for Good and Glasgow Credit Union have formed a partnership to address housing inequality in Glasgow and neighbouring areas. Glasgow Credit Union has provided a £2.4 million loan to Homes for Good, which will be used to purchase up to 35 homes for low-income individuals and families. The ...
15/11/2024
The historic Troon station has reopened following a £5m restoration project. The station was extensively damaged by a fire in 2021. Network Rail, in partnership with AmcoGiffen and CPMS, undertook the rebuild, which included the restoration of the station's iconic façade while incorporating modern ...
15/11/2024
BEAR Scotland, on behalf of Transport Scotland, is undertaking emergency works on the A828 between Ledaig and Benderloch to address a safety concern related to a deteriorating rock face. Recent monitoring has identified a fractured rock mass 60 metres above the road, requiring urgent attention. To ...