Work is underway on the first phase of Scottish Water's £120 million drinking water investment programme in East Renfrewshire and Ayrshire.
Pipe installation works are being carried out for a 13 mile-long strategic water main from near Newton Mearns to the Fenwick/Waterside area.
The scheme follows 18 months of preparatory work, including the creation of a strip for the water main to be installed, and involved close liaison with landowners and statutory bodies as well as detailed ecological studies.
Scottish Water contractors are now setting up welding areas and excavating five metre-deep trenches before using a crane to lower 12 metre-long sections of pipe into place.
It is expected the water mains construction will take around four years and will create a 'larger, more robust' connected supply.
Other sections of new mains include a section of about 13 miles from the Fenwick Waterside area to Dundonald in South Ayrshire and a section of about six miles from the Pollok area to a reservoir storage tank in the south of Glasgow
Stewart Davis, Scottish Water's programme manager, said: "We are delighted to have completed all the preparatory work for this section of main and to have started the construction phase.
"This is a major piece of work on the first phase of Scottish Water's overall investment in improvements to connect the system in Ayrshire with the Greater Glasgow area's network."
(LM)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
26/11/2024
Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024
The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024
First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024
A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024
Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024
The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024
West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024
Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024
Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024
Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...