A major milestone has been reached on the £1.35 billion Queensferry Crossing project.
The final section of bridge deck is set to be lifted into place today, 03 February, marking the completion of the 1.7-mile deck span between Edinburgh and Fife.
With 122 deck sections, each weighs around 750 tonnes. In total, 77,200 tonnes of steel and concrete has been added to complete the deck of the new bridge, with 1,868 metres lifted across this part of the bridge which is 2,633 metres in length in total (including the approach viaducts on the north and south).
Economy Secretary Keith Brown said: "The public have been fascinated by the spectacular progress on the Queensferry Crossing. While there is a lot of work left before opening to traffic in May, completing the deck represents a true landmark moment that we've all been looking forward to.
"It's the moment Fife and Edinburgh are connected by a third, stunning structure across the wide waters of the Forth. It's a privilege to be here to see it.
"Every time I visit the bridge I'm struck by the expertise and endeavour of the workforce. Today is a hugely important milestone, one everyone involved should be very proud of. I'm sure I speak for many of us when I thank them all for their continued hard work and this fantastic progress."
Michael Martin, Project Director for Forth Crossing Bridge Constructors (FCBC), added: "This final deck lift is the culmination of a world class team effort stretching all the way back to the very first day of construction in 2011.
"The final "closure" is always one of the most significant milestones in any bridge construction programme.
"We are now focused on completing the huge range of finishing works and bringing the Project to a successful conclusion."
Following this phase, focus will shift to completing the concrete deck of the south approach viaduct and making the full and final closure of the bridge deck from end to end.
The Queensferry Crossing is due to open in May 2017.
Video of the lifting of the first 12 pieces of deck by at floating crane.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
26/11/2024
Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024
The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024
First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024
A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024
Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024
The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024
West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024
Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024
Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024
Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...