Network Rail has announced that they are set to begin works to lay the foundations for the electrification of the Levenmouth Rail Link.
The first phase of work between Thornton Junction and Haugh Mill Lade will see the project pile foundations for masts that will carry overhead wires in readiness for the introduction of quieter and more environmentally friendly electric trains.
Work to install the piles will begin on Monday October 24 and will last for circa three weeks as the first piles are inserted to the west of the rail corridor - mostly during day-time working. One night of overnight piling will be required for locations closest to Thornton Junction and this is scheduled for Saturday October 29.
Further piling along the Levenmouth rail corridor is being programmed so that it works in tandem with other activities on the project, such as work on bridges and track laying.
Piling is an essential part of laying the foundations for the newly electrified railway and it is among the noisiest work activities on the railway and can be disruptive. Homes closest to the work sites have been notified by letter to make them aware of the possible noise.
While the work is being delivered as part of the reinstatement of the branch, electrification of the line to Leven is part of the wider electrification of the railway in Fife as part of the Scottish Government's plan to decarbonise passenger services on the network by 2035.
Work on the Levenmouth Rail Link is scheduled to complete in spring 2024 and services will initially be in introduced using diesel trains. By this point however, the line will be future-proofed to enable the introduction of Battery Electric Multiple Units (BEMUs) to replace life-expired diesel units which will be phased out on completion of the wider Fife electrification project.
Sean Clemie, earthworks and structures lead for the project said: "The first piles going into the ground in the Thornton area is big for the project but also an important milestone for the wider aspirations to decarbonise the railway across Fife.
"With the first mile of the Leven branch already operational railway, we can use this to move the track-based piling rig to each location to sink the foundations and then insert the masts that will ultimately carry the overhead wires that will power the railway.
"The start of this phase of work is another sign that the project is really taking shape. It's an exciting step forward for the team as we work towards delivering an electrified railway for Levenmouth and in creating an even greener, cleaner, and more reliable railway for Scotland."
Time and date
CONSTRUCTION DIRECTORY
Construction News
18/10/2022
Levenmouth Rail Link Electrification Works To Get Underway
Latest Construction News
26/11/2024
Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024
The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024
First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024
A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024
Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024
The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024
West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024
Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024
Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024
Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...