10/11/2022

Latest Phase Of Rothienorman Substation Development Set To Begin

Construction News Image
SSEN Transmission has announced that the second of two major components in the development of Rothienorman Substation is set to arrive at the site this weekend.

Following on from the successful arrival of the first transformer in October, the SSEN Transmission team is gearing up for the delivery of the final transformer to Rothienorman Substation as part of the second phase of major work at the development.

Working with principal contractor Balfour Beatty, the project involves upgrading the existing infrastructure at the substation from 275 kilovolts (kV) to 400kV, this increased capacity will help accommodate the connection of more renewable generation from across the north of Scotland, playing a key role in the transition to net zero emissions.

As part of this, two surpergrid transformers - each weighing around 130 tonnes - along with the associated equipment and components will be installed at Rothienorman Substation, with the first of the units successfully delivered in October.

-- Advertisement --
NorthernAsbestosServicesLtd

The next transformer will be delivered on Sunday 13 November and will follow the same format as the first delivery, with specialist haulier Rawcliffe transporting the 130-tonne unit via convoy using a large 12-axle specialist vehicle under the guidance and supervision of Police Scotland. The transformer will depart from Aberdeen Quay at 8am and make its way to Rothienorman substation via the A96, A920 and B992.

Due to the size of the transformer, the delivery vehicle will be travelling at a reduced speed for safety, and it is expected the journey will take between three and five hours. No road closures are required to facilitate the movement of the transformers, and vehicles should be able to pass the convoy at regular opportunities on the road network under guidance from Police Scotland, when safe to do so.

SSEN Transmission Project Manager Arthur Sinakov said: "We're gearing up for the second and final delivery of our major supergrid transformers, which are key components in our ongoing Phase Two development at Rothienorman Substation.

"The first transformer was successfully delivered with minimal impact to road users last month, and safely arrived at the site in just under three hours from Aberdeen Quay. The second unit will be delivered in the exact same planned route as before, and we aim to complete the complex delivery as quickly and safely as we can.

"As ever we want to thank the local community in advance for their patience and understanding while we transport these transformers onto their final location in Rothienorman."

Construction of the substation, located around two miles west of the village of Rothienorman, began with Phase one in 2019, and is part of a wider strategy to reinforce the transmission network in the North East and East Coast of Scotland to accommodate increased renewable energy generation, helping to deliver a network for net zero.



Latest Construction News

26/11/2024

Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024

The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024

First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024

A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024

Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024

The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024

West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024

Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024

Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024

Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...
RBT Underfloor LimitedMorris & Spottiswood LtdSEEIT3DCF Concrete PumpingMaccaferri LtdDiscount Kitchens and Bathrooms LtdShopfronts ScotlandJSJ Foam Insulation LtdEarth Tech LPS LTDSolway Ecology Consulting Ltd
Terms and Conditions
2024/11/26 14:36:38