Network Rail has launched a £6 million project to regenerate a 175-year-old Perthshire railway tunnel.
More than 3,690 new plastic sleepers were laid during engineering work to renew the track which was successfully completed on Tuesday, February 27, following three short closures of the line during February.
It's the first time that composite sleepers – which lay on top of the ballast, hold up the rails and keep them the correct distance apart – have been used at such volume anywhere on Scotland's Railway.
Trains couldn't run while work took place but have now returned following the £6m investment in the project, which will keep the railway reliable for years to come.
During the work, 10,860 tonnes of ballast, around 6000m of new rails, and 448 concrete sleepers were also laid on both lines.
At over 1000m long, Moncrieffe tunnel - which first opened in May 1848 - is the fifth longest and one of the oldest railway tunnels in Scotland.
Craig Barclay, operations director, said: "The work we've completed at Moncrieffe tunnel will keep the railway, and train services, as reliable as possible now and in the future.
"While the tunnel has had a long and very significant history, we've used innovative and modern technology that'll keep trains moving on what is a vital route on Scotland's Railway.
"We thank passengers for their patience while we carried out the work."
The recycled composite sleepers will help Network Rail in its aim to achieve a net zero carbon target by 2035.
The sleepers also offer a significant life cycle of 50 years and when they are eventually replaced, they can be re-used, re-purposed or recycled to make new sleepers or other composite products.
Time and date
CONSTRUCTION DIRECTORY
Construction News
29/02/2024
Network Rail Invests £6m In 175-Year-Old Perthshire Railway
Latest Construction News
26/11/2024
Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024
The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024
First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024
A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024
Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024
The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024
West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024
Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024
Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024
Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...